News brief: Downtown Lowdown

Wednesday, Thursday & Friday:
Pavement installed downtown all three days. First section: S. Broadway from M-24 north to Flint St. Second Section: W. Flint St from M-24 east to Broadway. Third Section: N. Broadway from Shadbolt south to Flint St. Last Section: E. Flint St. from just east of Anderson St. Once cooled, traffic will be allowed.

Wednesday, June 15, Work will continue on S. Broadway from M-24 to Front St. Electricians, and sidewalk installation continues in this area. Front St / Broadway St. alley will be open in both directions. Brick paver installation will continue downtown. Pavement milling in preparation for the new blacktop should start on or around June 20.