Bridge still not done

Bridge still not done
Anlaan Corporation asked and received a one week extension from village officials to complete work on the new North Shore Bridge.
Originally, the project was supposed to be done by Labor Day. A time extension was needed because Consumers Energy took a week to relocate a gas line. Work on the bridge couldn’t move forward until the relocation was complete.