School construction projects moving along

At the Feb. 14 Clarkston schools board meeting, Supervisor of Building and Grounds Department Wes Goodman presented an update on the current construction sites located at Clarkston Junior High, Sashabaw Middle School and the Early Childhood Center.
According to Goodman, the construction is moving along very well. Clarkston Junior High is about 40 percent complete, Sashabaw Middle School is ahead in certain areas but behind in others and the Early Childhood Center is also right on track.
The area of Sashabaw Middle School that is behind is the roof. Due to the latest weather conditions, contractors are only able to work on portions at a time. Currently, this is the best method to develop and complete the roof.
All construction sites are due for completion by the beginning of the 2005-06 school year.